Leo Lemay and his crew started laying logs August 24, 2009
|

Gil's Construction poured footers July 9, 2009
|

Maxwells Truckin' working July 22
|

Gate made by Awesome Welding installed August 1, 2009
|

Mooseprints through the center of the future building. He stepped right over the footerwall and onto the sand, walked right through the office!
|

Gosselins Water Wells set up August 18. Water found at 354 ft / 8 gpm
|

UTG Parking Area August 18 2009
|

June 26, 2009 Surveying the site - Robert Maxwell, Leo Lemay, Howard Walker
|

The UTG office in Ferdinand is located about 1.6 miles east of the Brighton Airport on VT105. This is a view from Paradis Mountain Road in Brighton.
|

Progress as of August 27, 2009
|

Progress as of 10/19/09, bringing parking lot up to grade.
|
ct192009.jpg)
Inside progress: Vault to the back left, framing done on kitchen, bath, and mechanical room.
|

New slate installed on front porch Oct 29, 2009
|

Vermont Slate up close
|
|